Curtin University - Stage 2
CLIENT
Curtin University
LOCATION
Bentley
VALUE
$7 million
TYPE
Construct only
The project extended the life of the Design and Arts Precinct (DAP) for a further 10 years.
Delivered in four, staged separable portions (SP) to enable the ongoing use of the precinct, works involved refurbishing existing buildings, adding new learning spaces, and external works and landscaping:
SP 1 (five months) – demolition and refurbishment to accommodate new computer laboratories
SP 2 (three months) – demolition and refurbishment to provide a new communications room, new prototyping studio, upgraded informal learning areas, hopper relocation, electrical/communication upgrades, external ramp in the courtyard, and upgrade to a new fire wall
SP 3 (six months) – demolition and refurbishment to accommodate new workplaces
SP 4 (10 months) – demolition and new build/extension to provide new learning facilities and external works, including the relocation of several mature trees.
'(EMCO Building) operated in a professional manner at all
times and demonstrated a positive ad proactive role
throughout this challenging project. We were very pleased
with the quality of the finished product. (EMCO) paid
considerable attention to time and cost performance.'
Project manager